Foundations are the one part of your villa you will never see once it is built, yet they carry everything above them for the life of the building. Many owners hear terms like "isolated footings" or "raft" without knowing how they differ or why the engineer chose one. This guide explains the common foundation types used in Riyadh, why the soil report has the final word, and what to check before any concrete is poured.
What foundations actually do
A foundation transfers the building's loads, from the concrete frame and walls to furniture and occupants, safely into the ground. "Safely" means two things:
- The pressure must stay within the soil's bearing capacity, the load per unit area the ground can take without failing or compressing excessively.
- Settlement must be small and even. Every building settles a little. The real problem is differential settlement, when one part sinks more than another and cracks appear in walls and floor tiles.
So there is no single "best" foundation. There is only the right one for this soil, these loads and this design.
The four common types
Isolated footings
The most common choice for Riyadh villas. Each column sits on its own reinforced concrete pad, usually square or rectangular. The footings are normally tied together with ground beams (known locally as meed), which connect the column necks, limit relative movement and support the ground-floor walls. Isolated footings suit reasonably good soil, moderate loads and columns spaced well apart.
Combined footings
When two columns are so close that their footings would overlap, or a column sits right on the boundary so its footing cannot extend outward, the engineer designs one footing to carry both. Edge columns may also use a footing tied back with a strap beam.
Strip foundations
A continuous strip of concrete under a load-bearing wall or a line of columns. You will see them under boundary walls, in load-bearing wall structures and wherever the engineer wants to spread load along a line. We cover the boundary-wall case in building boundary walls.
Raft foundations
A raft (or mat) is a thick reinforced slab under all or most of the building, carrying every column together. It spreads load over a large area, lowering soil pressure and reducing the risk of differential settlement. Engineers tend to choose a raft when:
- the soil's bearing capacity is low;
- the isolated footings needed would be so large they nearly touch;
- there is a basement or a groundwater level that calls for a continuous, easily waterproofed base;
- soil properties vary across the footprint.
Side-by-side comparison
| Type | Typically used when | Site points | Relative cost |
|---|---|---|---|
| Isolated footings | Good soil, moderate loads | Accurate grid and levels, tied with ground beams | Usually lower |
| Combined footings | Close or boundary columns | Top and bottom steel as designed | Medium |
| Strip foundations | Load-bearing walls, boundary walls | Continuous steel and level | Lower to medium |
| Raft | Weak soil, basements, heavy loads | More steel and concrete, a large organised pour | Usually higher |
Treat the cost column as a rough guide only: a very large isolated footing on weak ground can approach a raft in quantities. The real answer comes from a take-off on your actual drawings.
Why the soil report decides
A soil investigation is carried out by a specialist lab. It drills boreholes, samples the ground at different depths, tests the samples and gives recommendations to the structural engineer. The key outputs are:
- Soil layers: what each layer is (sand, silt, clay, rock, fill) and how thick.
- Allowable bearing capacity at a given depth.
- Recommended founding level.
- Groundwater level, if any was found.
- Special warnings: old fill, soils that collapse when wetted, expansive soils, or salts that can attack concrete.
- Recommendations on foundation type, cement type, and any replacement or compaction needed.
Without it, the engineer has to assume. In foundations an assumption is either too cautious, adding steel and concrete you did not need, or too optimistic, exposing the building to settlement and cracking.
Riyadh soils: a general picture, not a diagnosis
There is no single "Riyadh soil". The city is large and ground conditions change from district to district, sometimes between neighbouring plots. Engineers here may meet:
- shallow limestone layers in some areas, usually good to found on but slower to excavate;
- sandy or silty soils elsewhere, which need their capacity and compaction checked;
- previously filled plots, where uncompacted fill is not suitable to build on directly;
- raised groundwater in some neighbourhoods, which affects excavation and waterproofing;
- cavities in certain limestone layers that need specialist treatment.
The point is not to diagnose your own plot, but to understand why a good contractor will not simply copy what the neighbour did. Your ground may differ, and only a report for your plot settles it.
From report to pour
Once the structural drawings are approved, foundation work usually runs like this:
- Set out the grid accurately and check it against the boundaries.
- Excavate to the founding level, removing weak fill or organic material, with replacement and compaction if specified.
- Treat the soil against termites with approved products. See why termite treatment comes before foundations.
- Lay the polyethylene moisture barrier and pour the blinding concrete, explained in moisture barrier and blinding concrete.
- Fix footing formwork and reinforcement with chairs and spacers.
- Fix column starter bars precisely on the grid.
- Engineer's inspection, then pour with proper vibration, then cure.
- Pour necks and ground beams, coat buried concrete with bitumen, and backfill in compacted layers.
What to check before the pour
- Dimensions and levels of each footing against the schedule on the drawing.
- Bar sizes, numbers and spacing.
- Spacers under and beside the steel to give the specified concrete cover, the layer of concrete that protects steel from moisture and rust. For elements cast against soil it is larger than for elements above ground, often in the range of 50 to 75 mm, as specified by the engineer.
- Clean steel, free of mud, oil and flaking rust.
- Starter bars on the grid and long enough to lap with the column steel.
Common mistakes we see: relying on a neighbour's soil report, founding on uncompacted fill, missing spacers, pouring at midday without precautions, and backfilling in one thick layer. Hot-weather pours are covered in pouring and curing concrete in hot weather.
How Marafi builds foundations
We work from the approved structural drawings and the soil report's recommendations, and we never change a foundation type or size without the design engineer. On site we treat the soil with approved termite products, lay the polyethylene sheet carefully against moisture and pour the blinding, then build the footings with precise dimensions, levels and starter-bar positions, strictly following the engineering drawings. Labourers, technicians, supervisors and engineers work together, and owners receive photos at each pre-pour inspection. See Foundations & Footings, and for basements or retaining walls, Infrastructure Works. The full sequence is on How we build.
Owner's checklist
- Get a soil report for your own plot and approved structural drawings.
- Ask the engineer which foundation type was chosen and why.
- Confirm termite treatment, moisture barrier and blinding before footings.
- Inspect steel, spacers and starter bars before every pour, with photos.
- Make sure buried concrete is waterproofed and backfill is compacted in layers.
Getting ready to build in Riyadh? Contact us to arrange a site visit and a review of your drawings and soil report, and we will send an itemised proposal as part of our Villa Construction service.
Frequently asked questions
Can I choose the foundation type myself to save money?
It is not advisable. The foundation type is a structural decision made by the engineer from the soil report and the loads. Your role is to understand the choice and make sure it is built to the drawing.
When is a raft foundation the right choice?
Usually when the soil's bearing capacity is low, when isolated footings would be so large they almost touch, or when there is a basement or a risk of uneven settlement. The structural engineer makes the call.
Do I really need a soil report for a small villa?
It is what the engineer uses to size the footings and set the founding level, and many offices and authorities expect one. Its cost is small compared with the consequences of a foundation mistake.
How do I find out what the foundations will cost on my plot?
Once the structural drawings and soil report are approved, a contractor can take off the quantities and give you an itemised proposal. It varies from plot to plot with the foundation type and depth.